Stacking starts...

On August 9th, the exterior walls of the lower level of the house started to take shape as the first of the ICE* foam blocks for the insulated concrete walls were stacked. A great deal of care is taken at this point to compensate for any areas where the foundation footings are not perfectly level.

* ICE (Insulating Concrete Efficiently) is the brand of insulated concrete forms used for our home. For more information about insulated concrete construction, see Technologies.

Photo - 8/09/02
View from our front porch.

Photo - 8/07/02
Galvanized "Shiny 90" was first anchored to create a channel for the blocks.
Photo - 8/09/02
The tongue-and-groove blocks are stacked over vertical steel rebar rods.
Photo - 8/09/02
The blocks have horizontal and vertical channels for concrete, and metal "studs" to anchor exterior and interior wall coverings.

Photo - 8/09/02
At the end of the day on August 9th, the lower level walls are started.
Corner blocks are gray.

Photo - 8/16/02
By August 16th, the lower level blocks are in place,
but this is just the beginning. The real work starts now.


Home | Beginnings | Flood | Foundation pour | Blocks & tanks | Cistern
Stacking | Pour preparation | Wall pour | Floor beams | Floor pan | Floor pour
Stacking II | Interior walls | Moving up | Decks | Upstairs | Roof | Roof II
Dogrun | Roof III | Sticks 'n stones | Decks II | Floors & windows | Sheetrock & stairs
Railing & siding | Texture & metal | Exterior | Cabinets & floors | Counters & such
Rainwater system | Dogrun II | Final stuff

Green Building | Technologies | Credits




©2002 Email: herb at moonmountaingroup.com
http://www.moonmountaingroup.com/home/stacking.html  -  Modified: Jun-04-03