At last, a roof...

On the morning of February 5th, the plywood sheathing for the exterior walls of the second floor is in place and work has started on the roof.

The sheathing is faced with heat-reflecting foil wherever it covers a wall exposed to the outside. The roof structure is comprised of manufactured I-beam rafters and 6" thick foam panels designed to provide a 2" air space under the decking for the reflective metal roof.

The previous day, we traveled to Seguin to see how the Spaceframe components are fabricated.

Photo - 2/05/03
By mid-morning on a gray,
rainy day, the beginnings of the
roof can be seen from the driveway.


Photo - 2/05/03
Rafters are secured with screws.
Note the reflective sheathing.


Photo - 2/05/03
After adjacent rafters are in place,
foam panels are installed by...


Photo - 2/05/03
...slightly spreading the rafters apart...

Photo - 2/05/03
... and dropping the foam into place.

Photo - 2/05/03
The R-24 foam rests within channels created
by the design of the rafters.


Photo - 2/05/03
Looking up in the guest bathroom...
Voila!, the ceiling takes shape.


Photo - 2/05/03
By the end of the day, a new look,
from the upper driveway...


Photo - 2/05/03
...from the approach
to the front entrance...


Photo - 2/05/03
...and from the Southwest corner.

And guess what?
Snow may be coming!




Home | Beginnings | Flood | Foundation pour | Blocks & tanks | Cistern
Stacking| Prep for wall pour | Wall pour | Floor beams | Floor pan | Floor pour
Stacking II | Interior walls | Moving up | Decks | Upstairs | Roof | Roof II
Dogrun | Roof III | Sticks 'n stones | Decks II | Floors & windows | Sheetrock & stairs
Railing & siding | Texture & metal | Exterior | Cabinets & floors | Counters & such
Rainwater system | Dogrun II | Final stuff

Green Building | Technologies | Credits




©2002 Email: herb at moonmountaingroup.com
http://www.moonmountaingroup.com/home/roof1.html  -  Modified: Jun-04-03